Tuesday, 6 May 2008

An actual new London Overground train

Reader Dazz285 has supplied me with another shot of a new London Overground train under construction (previously), this time much more recognisable:

You can see how wide the walk-through end gangways will be. It seems we won't be getting the fancy frameless windows the other air-conditioned models of Electrostar have.

Monday, 5 May 2008

GE19 bridge push: Day 2

After getting the GE19 bridge most of the way across yesterday, it was moved into its final position overnight. Here are some photos of it in its final position:

The extension on the front has ended up completely across Brick Lane:
It's not obvious in this picture, but the front extension curves upwards significantly. This meant as the bridge was pushed the front was lifted up, raising the bridge from the horizontal (how it was built) to a 1 in 30 gradient (needed to get the line over Brick Lane).

The area where the bridge was assembled:
If you look immediately underneath you can see the bracket where the strand jack was attached, and a corresponding hole in the framework on the ground that the cable was anchored to.

Inside the Bishopsgate Goods Yard compound:
The wall in the distance is obviously where the site borders Brick Lane. There's a fair gap between the under construction viaduct and the bridge, though the viaduct posts have been ready for a while. As far as I'm aware, the bridge over Brick Lane will simply be a concrete viaduct span rather than anything special.

Finally, a slightly wonky Autostitched panorama of the whole site:
From left to right: Bushes atop the Braithwaite Viaduct, Shoreditch High Street bridge (very small), Shoreditch High Street station, the extension, Brick Lane, the bridge, the bridge construction site, and just out of shot, Shoreditch tube station.

Sunday, 4 May 2008

The GE19 bridge push: Day 1

I was invited by TfL to use the official viewing galleries set up for this event, so I've had a very good view of the action.

I'll start with an overview of the site, taken from the east end:
This was taken around lunchtime after the bridge had been moved a fair distance, with the front dangling over the railway line.

While the wheels at the back are powered, the majority of the force comes from a pair of strand jacks:
These are basically just hydraulic rams that can pull themselves along cables. The two sets of cables are strung along underneath the bridge and anchored to the eastern abutment (ie they don't cross the railway line). The jacks should therefore roughly reach the end of the cable when the bridge is in its final position.

So that's the theory. Here's how it looked when I got there first thing:

The bridge had already been moved a significant distance, with the west end of the bridge proper (the brown bit) resting on the eastern abutment. The grey bit is a temporary extension and will be cut off and scrapped.

During the morning they moved it much further:

They then took a break to add a whole load of counterweights (kentledge) to the back. It started moving again:

With the tip of the bridge looming very close they started lubricated the western abutment:
The bridge is sliding on flat pads, with no bearings, though the pads are free to pivot front to back.

A short while later, the tip of the extension was hovering right over the pads:

This next bit surprised me. They were able to jack up the back of the bridge, tilting the opposite end down onto the pads:
Note that the left side touched down before the right. This caused a view anguished faces in the viewing gallery. It doesn't seem to have been a real problem, though they were briefly seen holding an ordinary builder's spirit level up against it.

They moved it a couple of feet further packing up:

I think they're now repositioning the counterweights. At time of writing it hasn't moved again, though you can watch the live webcam and be the first to know.

Thanks again to TfL for the invite.

Thursday, 1 May 2008

GE19 bridge move this weekend

The second of the three major bridges for the East London Line extension is being moved into place this Sunday and Monday. It's the GE19 bridge that crosses the Great Eastern Main Line (the line out of Liverpool Street), right next to where Shoreditch tube station was. See my map of the whole area.

This photo was sent to me by TfL's actually-being-helpful press office, which shows just about everything, taken from above Brick Lane looking east:
The building on the right is Shoreditch station, and the bridge is sitting where the platform cutting used to be.

The accompanying info says the best place to view the move is Allen Gardens (a short walk from Whitechapel station). Regarding when to go:

The best times to see the bridge actually moving are expected to be Sunday 04:00 to 07:00, 09:00 to 12:00 and 17:00 to 22:00 or Monday 04:00 to 08:00, but are of course subject to progress on site and weather.
The bridge will be moved using "strand jacking", which is where a hydrualic ram is used to pull on a steel cable. Once the ram is fully extended, it's disconnected from the cable, retracted, and reattached further down the cable, so the process can begin again.

They say the structure to be moved weighs 1800 tonnes including "kentledge", which is your new word for the day.

Update: The east end is on wheels!
This must be the self-propelled vehicle mentioned here. The strand-jacking is how the front will be winched across.

Wednesday, 30 April 2008

Bank-Monument: TfL mellows out

So on Monday morning London Underground were handing out an amazing little booklet at Bank station:

That's it on the right, next to their earlier snotty dictatorial attempt at public relations.

They've managed to produce a nice, well-illustrated, detailed look at the history of Bank and Monument and a reasonably detailed overview of the escalator refurbishment programme*. It's informative, relevant, well-written and borders on being friendly in places. It doesn't even contain any outright lies.

Let's look at some quotes:

There will be no interchange at Bank and Monument stations
vs
Customers are advised not to interchange at Bank and Monument stations
Or:
Remaining walking routes through the station will change significantly, so please use nearby Cannon Street, London Bridge, Mansion House or Moorgate stations
vs
To minimise disruption we are endeavouring to keep as many walking routes as possible through the stations open.
But the most astonishing thing about the new leaflet is how it closes:
We apologise for any inconvenience caused to your journey.
Disingenuous or not, there wasn't anything even resembling an apology before.

[* though not as detailed as it could be]

Tuesday, 29 April 2008

Oyster PAYG on First Great Western could be due in May

An anonymous tipster points me to this set of London Travelwatch minutes, which say:

Meeting with First Great Western (FGW) and Passenger Focus to discuss implementation of Oyster pay as you go on FGW. This was on schedule for May 2008 – nine months ahead of most other train operating companies (TOCs).
An early rollout was mentioned at another London Travelwatch meeting.

First Great Western recently started accepting Oyster PAYG between Greenford and Ealing Broadway, with an extension to Paddington due soon. This announcement appears to allude to all their London services. It may also include Heathrow Connect as far as Hayes & Harlington, since that portion is technically a First Great Western service.

I also note 9 months from May is February 2009, which is either a miscalculation or they're expecting other companies to miss the advertised January date.

Imperial Wharf funding plan approved

Last night Hammersmith & Fulham council approved the funding plan for Imperial Wharf station, which means everything is in place for the station to go ahead, with construction starting later this year, and opening in 2010.

The station will be located on an embankment section of the West London Line between West Brompton and Clapham Junction, and served by London Overground and possibly Southern.

[Update: Southern trains that on the WLL will call at all stops except Imperial Wharf, according to themodel timetable for the North London Line upgrade]

The entrances will be on Townmead Road, which is the road passing under the new bridge* by the bus in the photo above (taken from the southwest). The ticket office will be located within the old bridge to the right, with ticket barriers and stairs up to the platforms either side. I did once locate the planning application which showed all this in detail, but it's alluding me right now - the rendering on Always Touch Out sort of shows the set up.

(* which the Railtrack signs call "Yuppies". It appears to have been built for access to the luxury flats in the photo. Is there a story here?)

[Thanks, anonymous commenter]

Monday, 28 April 2008

Finsbury Park station upgrade plans

I've been over the plans to install ticket barriers and lifts at Finsbury Park station before, but I saw on TfL's project page they've taken the unusual step of pointing passengers to the planning application, which comes with a long list of documents and plans.

The design statement will tell you everything there is to know about the proposal, including photos of disused parts of the station. It suggests Network Rail may install lifts up to their platforms at the same time, and gives serious consideration to Islington Council's Western Ticket Hall proposal. One odd detail mentioned is the spiral staircases need to have their direction reversed.

The northbound and southbound cross-sections show just how shallow the tube lines are at the station, and where they're located in relation to the rail platforms above.

The future site plan shows a set of doors enclosing the Station Place entrances. This certainly doesn't exist now and isn't part of the works in this planning application, so I'm not sure what that's about.

Finally, TfL's site says the application is still pending, but it was actually approved on April 4th.

Shepherd's Bush Overground hole getting bigger

The work to widen the platform at Shepherd's Bush seems to be moving ahead quickly):

It was barely started last Tuesday. They only seem to be bothering with the southern half of the platform, nearest the station building, at least for now.

And it's nice to see the station finally being used for something, even if it's just as a site office:

The Imperial Wharf council meeting

Today's council meeting that could have finally given the green light to Imperial Wharf station seemed too momentous an occasion to miss, so I popped along, and this is what I found.

I was going to make a joke at their expense, but then I spotted this in the agenda:

The Cabinet is invited to resolve [...] that the public and press be excluded from the meeting
So that was a waste of time*. We'll just have to wait for the press release.

Anyway, the budget contains a lot of juicy information anyway. They've acquired a huge pile of cash:
• The Committee also agreed to reallocate to the station £750k of Section 106 funds initially earmarked for expansion of primary schools required for Imperial Wharf but no longer considered to be necessary. This, together with interest earned on the station Section 106 account since 2000, amounts to a total of £4.25 million available from St George
• £1 million from Transport for London complementary measures for the western extension of the congestion charge (already received and with interest accruing).
• £1 million from the Lots Road power station development, payable on commencement of development on the land in Hammersmith and Fulham.
• Up to £650,000 on offer from the Royal Borough of Kensington and Chelsea (subject to a Council decision)
• £300,000 Section 106 funding from Chelsea Harbour design centre, payable upon commencement of development.
• £60,000 Section 106 funding already received (with interest accruing) from Sainsbury’s, Townmead Road.
That's over £7 million. The final price for the station is a secret (though it was £7.93m), but Hammersmith & Fulham Council are apparently willing to pay the remainder, including if any of the above deals fall through. They'll be paying St George to handle construction of the station. Network Rail and Transport for London don't seem to be involved at all, beyond being consulted on the design.

* It does also say "Members of the Public are welcome to attend" in bold on the front page, so I am quite grumpy

Sunday, 27 April 2008

Shadwell DLR platform extension nearing completion

For whatever reason, Shadwell is getting its platform extended to take three cars long before most other stations. I was passing through and spotted this muddy hole in the ground is a bit of surfacing away from being a proper platform:

There was a reference to "Shadwell Track Slew Completed: May-08" in the recent board papers, which is probably a reference to the eastbound track not being in line with the platform:

In other platform extension news, most stations on the Poplar-Stratford route now have their extension boundaries marked out with blue fencing.

Don't got too excited though. I've just noticed the official completion date has been officially pushed back to early 2010 (not just unofficially). And if you live on the Beckton branch, sorry, you're not included.

Stratford station photos

The official London 2012 blog has an post on the upgrade works at Stratford station, with a couple of vaguely interesting photos. 

Saturday, 26 April 2008

DLR improvement works

I've been emailed  a document that includes several interesting bits about DLR current projects, mainly regarding service changes during it.


Royal Mint Street Junction remodelling. This is where the Tower Gateway and Bank branches split. Currently the route to Tower Gateway is a single lead design which limits capacity, and the two tracks west of there are used bi-drectionally to reach each platform, rather than one for eastbound and one for westbound. Hopefully these two problems will be fixed - they'll have to be given Tower Gateway will in future only have one platform.

Single-line working south of Crossharbour. For two months starting this June the Stratford-Lewisham service will terminate at Crossharbour and the Bank-Lewisham service will terminate at Island Gardens, with cross-platform interchange to an Island Gardens-Lewisham shuttle, as well as parallel bus services. These services will only use one track, enabling the platform extension work to take place on the other.

Canning Town junction rebuild. The new junction for the Stratford International Extension is going in east of Canning Town. From 21 April trains from King George V go to Tower Gateway and trains from Beckton terminate at Poplar. From 30 June trains from King George V switch back to Bank, with Beckton services cut back further to Canning Town. This doesn't seem to reduce the number of trains over the junction, but whatever.

Bank station closing. For 5 weeks starting Christmas Day 2009, Bank will be closed for works relating to the three-car project. This appears to indicate a delay in the start of three-car running (scheduled for late 2009).

Bank-Monument escalator works

It looks there's a lot more work planned for the escalator refurbishment at Bank and Monument. I've been sent some info that gives details of the full programme:

  • April 2008-Autumn 2009: DLR-Monument (E12-13 and E14-15). These are the ones currently closed.
  • September 2008-June 2009: Northern Line-Monument (E4-5), one at a time. If the remaining one fails the Northern Line will have to non-stop Bank due to lack of evacuation routes.
  • May-October 2008: Lombard Street ticket hall escalators (E6-7), one at a time.
  • Late 2009-Autumn 2011: DLR to Bank (E8-9 and E10-11). These have already been worked on, but it seems it was life-extending maintenance, and this will be the full replacement.
  • TBD: Main Central Line escalators (E1-3)
(The map I made of the station has the escalators and their numbers marked on)

The presentation notes that the DLR escalators are being replaced so early in their life (17 years) due to much heavier usage than anticipated.

The E4-5 works will mean there'll actually be no Monument to Bank interchange, though Bank to Monument should still be a goer. One of the E6-7 escalators is closed already, so that work shouldn't make things any worse at the Bank End. In fact, things are better since I made that last map - the spiral staircase route has been open every time I've been there.

Tuesday, 22 April 2008

Shepherd's Bush Overground platform widening begins

Ain't it a lovely day today? The sun is shining, Imperial Wharf is being built, and they've started digging a hole behind the legendary wall at Shepherd's Bush Overground:

Inside the ticket hall, they've put up fences and boxed up the gates:

This is the first time anything at all at the station has changed in six months.

(And yes the lift and the station signs are still pointlessly switched on)

[Thanks to Dazz285 for the tip off]

Shepherd's Bush Central Line update

They've started putting the western half of the frame (in the background), plus the internal walls for the staff accomodation:

Ever seen a brand new escalator on the back of a truck?

Thought not.

Imperial Wharf to open by 2010

The flood of press releases does contain one interesting statement:

There are 73 stations on the London Overground network; 50 on the North London Railway with two new stations due to open on the West London line by 2010 and 17 stations on the East London line with four new stations due to open in 2010
One is obviously Shepherd's Bush, and even that saga should be over soon. So we're looking at a timescale - however flimsy - for the construction of Imperial Wharf, which we haven't heard anything about since October.

The station also makes an appearance in the provisional future timetable. There's still hope.

Update: More than just hope (press release) [Thanks D-Notice]

Monday, 21 April 2008

London Overground station improvements

Friday's premature adulation of Homerton station has become not one but five near-identical press releases, covering: 

Crouch Hill is listed at the bottom of each release, but isn't worthy of a headline. The improvements are:
stations have been thoroughly cleaned and re-painted. The existing equipment including the public announcement and CCTV systems, information screens and lights have also been checked and repaired where necessary.
So no upgrades yet, just cleaning and repairs. Exactly what I found at Homerton.

(If, like me, you're wondering why they're announcing this now rather than waiting until all the stations are finished - most are coming along nicely - it seems this was an incoherent attempt to mark the 6 month anniversary of Overground, which was a week ago. Well done TfL press office)

Mitcham Eastfields latest

View all posts about Mitcham Eastfields

With the opening of Mitcham Eastfields allegedly only a month away, it's time for another visit.

Here's an overview of the site, looking south:

The station building and the northbound platform:

The liftshafts, footbridge columns, and the very end of the southbound platform:
(NB This blog does not endorse the commandeering of handy nearby tall buildings for photography purposes. Unless, of course, there's no one about)

So since three weeks ago they've put up equipment rooms for the lifts as well as pillars for the footbridge to stand on - but still no bridge. The station building has gained eaves and the canopies on both platforms look finished but unpainted, and the platform edging looks complete. The empty end of the building is where the ticket office, toilets and so on will be. Either it's all going to arrive in one piece on the back of a lorry, or they have a lot of work to do.

ELL phase 2 funding approved?

Now here's an interesting possibility. Reader Phillip Baker points out a comment Ken made during a TV debate, during a discussion of the news blackout rules that prevent announcements being made in the run up to an election:

And then also let's announce the government's going to let me build the East London Line to Clapham Junction, because we can announce that as well, if we're doing the good news
So was he trying to say it has been approved, but the rules prevent it being announced? Or was he just making an awkward hypothetical? Watch it for yourself - it's only a couple of minutes in.

You may also like to consider Peter Hendy's "watch this space" comment and the suddenly coy mention of the project in the last set of board papers.