Shepherd's Bush Overground: Finished!

Well almost. These men are putting the last bits of trim onto the aluminium panels that cover the rebuilt part of the station building:
You can see in that picture there are still some bits of back fence to do, and there's some tidying up of the work of the other platform, but I can't see them spinning it out for more than a couple more weeks.

In that spirit, here's an attempt to recreate the very first picture I posted of the station, last October, so you can see the difference:

And here's the widened bit and the non-widened bits of the platform together:


Update: According to the latest TfL board papers, opening is pencilled in for October 1. [Thanks to D-Notice in the comments]

Finally, a bonus picture of the enormous new Shepherd's Bush Central Line station:

Sunday, 27 July 2008

Shepherd's Bush/White City/Wood Lane interchanges

When the new stations at Shepherd's Bush and Wood Lane open there'll be two new out-of-station interchanges, requiring a short walk outdoors to change between lines. But how short?

Interchange #1: Shepherd's Bush (Overground) to Shepherd's Bush (Central Line)
Just across the bus station.

Approximate gateline-to-gateline walking distance: 100 metres.

Interchange #2: Wood Lane (Hammersmith & City Line) to White City (Central Line)
A stroll along Wood Lane right past BBC Television Centre.

Approximate gateline-to-gateline walking distance: 230m.

Friday, 25 July 2008

Wood Lane aerial photo

Following on from the photos I posted earlier this week, here's a great aerial photo of Wood Lane station taken by reader Former Optimist, presumably from the roof of BBC Television Centre:
There can't be many tube stations with another line they don't serve passing underneath the ticket hall.

Thursday, 24 July 2008

Rebuilding Tottenham Court Road station

Tottenham Court Road station is being massively rebuilt and expanded over the next 8 years - both to accomodate Crossrail and increase capacity - and an exhibition about what they're doing opened at New London Architecture today.

Here's the money shot (click to enlarge):
(1) is the new Crossrail platforms; (2) is a new escalator down to the Northern Line platforms; (3) is Crossrail's Oxford Street entrance (which looks like this inside); (4) is an escalator down to the Crossrail platforms, obscured by a new ventilation and emergency stair structure; (5) is the massively expanded ticket hall; and (6) is a new set of escalators down to the Central Line.

To build this, they've got to dig up a big chunk of the West End:
The right half of the site is the plaza outside Centre Point, while the left half is a block of buildings to be demolished - including as noted, The Astoria. In the middle is where the top end of Charing Cross Road currently is. They'll also be demolishing the block to the south of Sutton Row to build the Crossrail ventilation shaft (4). Everything currently on the site of the western ticket hall (3) will also be going.


The timescale for this is glacial, with preparatory works long since started, demolition and construction beginning next year. The new piazza entrance (on the southeast corner) opens 2013, and the piazza itself opens in 2015. Charing Cross Road will be diverted from 2010 until 2014. Construction at the station won't be finished until 2016.

In contrast, the exhibition lasts only until August 9.

Tuesday, 22 July 2008

Shoreditch High Street station box going up

As previously reported here, the East London Line extension's Shoreditch High Street station is to be enclosed on all sides by a massive windowless concrete box (i.e. walls and a roof). The primary aim of this is to protect the line so that it can stay open during the construction of skyscrapers alongside it.

Until now there was no sign of it, but this week they started erecting posts to support the structure:
It really is that big compared to the poxy humans.

Thanks to Antonio for the photo. Here's a panorama of the whole of Bishopsgate Goods Yard, using pictures taken by him today from the Tea Building on the north side of the site (click to enlarge):

The box will stretch at full height for the length of the platforms (which corresponds to the finished section of viaduct), and at a lower height all the way to Brick Lane on the left and Shoreditch High Street on the right (a map of Shoreditch, if you're lost).

Sunday, 20 July 2008

Wood Lane station progress

London's last new tube station is in the final stages of construction, ready for opening in October.

They've finished most of the external panelling:
If you click to enlarge you can see they've installed the external roundel, currently badly hidden by a black bin liner.

Down in the cutting is the Central Line, and the south end of the platforms at White City are a just the other side of the bridge on the left. Still probably not going to be marked as an official interchange.

The station building:
The pavement level has been raised far above road level here, for reasons unknown.

The platform signs are now visible from passing trains. Here's the roundel:

And the destination sign:
This shows the renaming of Shepherd's Bush (H&C) to Shepherd's Bush Market that will occur when Shepherd's Bush on the Central Line reopens, or when this station opens, or possibly it'll all happen at the same time.

Friday, 18 July 2008

Photo of new train for District/Circle/H&C/Met

Go here to see what I think is the first actual photo of one of the new S Stock trains. By 2015 these will be running all services on the Circle, District, Hammersmith & City and Metropolitan Lines, with the first in passenger service some time in 2010.

[via District Dave]

Thursday, 17 July 2008

Another East London Line bus disappears

London Underground are thinning out the East London Line replacement bus service again:

From Saturday 19 July 2008, bus service ELS, between Whitechapel and Shoreditch (Bethnal Green Road) will be permanently withdrawn. Route ELW will be extended to serve Shoreditch on Sunday mornings and during Monday to Friday peak hours.

From Monday 21 July the ELC frequency will be reduced to every 10 minutes in peak times.
Member Dstock7080 on the District Dave forum reports the ELW will also be downgraded from double to single deckers.

The cuts are probably due to the small number of people using the services (which is puzzling, given they do not collect fares). ELS is the oldest of the routes, having started in June 2006 when Shoreditch tube station closed, and I've never seen anyone on it. The ELC runs between Canada Water and New Cross, and likewise seems to be poorly patronised.

This follows the withdrawal of route ELP in February, probably because it was duplicated by the more frequent Route 381, which became the official replacement bus. Tube ticket acceptance on the 381 has now been extended to Surrey Quays, along the route of the ELC.

(there's a map of the new routes on the last page of the brochure linked above)

Wednesday, 16 July 2008

Shepherd's Bush Central Line station closure documents

Andy Slaughter MP has been doing some digging on why Shepherd's Bush Central Line station closed so suddenly earlier this year. Using the Freedom of Information Act he's got hold of a whole stack of internal documents. While they fill in few new details, the story laid out is pretty much what we knew already. The original plan was:

  • Westfield, developers of the new shopping centre, were due to replace the station building before the shopping centre opens, keeping the station open as far as was possible.
  • At some point, a new high-capacity staircase would have been installed down to the platforms, in conjunction with step-free access and other below ground works (BGW).
  • Metronet were due to replace the escalators in the period 2010-12. There was a possibility that if one escalator could be kept in service ("there have been engineering differences of opinion on the feasibility of this"), combined with the new staircase the station could remain open.
Fast forward to late November last year with the centre's opening less than a year away, work on the station not started, the BGW programme looking increasingly unfeasible, and Metronet in administration. Westfield made London Underground an offer: let us close the station so we can get the building replaced on time, and we'll replace the escalators for you while we're at. After some deliberation, TfL accepted.

That's a picture of the new ticket hall I've posted before. Thanks to reader Tim for the tip.

A few more West Hampstead Interchange details

In recent months plans have emerged to improve the interchange at West Hampstead in conjunction with the upgrading of the Thameslink station that will be done for the Thameslink Programme.

The various parties actually held a meeting last October but minutes have only just been made available, with lots of new details. The proposals are:

Thameslink Station – a new entrance on Iverson Road and new footbridge to west where platforms are wider to allow lifts. Existing entrance would remain open for people to/from the north. This will reduce pressure on West End Lane (WEL) pinch point.
NLL station – saw off front with a modest development to south at the same scale as current buildings.
West End Lane (WEL) – Make carriageway a uniform 7 metres all the way through and improve the public realm (footways on the west side) and crossings. Fully signalled junction with pedestrian crossing at WEL/Blackburn Road and widened footway between there and to beyond the NLL station would be provided.
The new crossing provides access to the tube station, which will remain on the other side of West End Lane. I've made a quick mockup of the changes in Google Maps. One victim of the scheme - and likely source of contention - is the trees between Iverson Road and the Thameslink station, because at least some of which will need to be removed to make way for the new entrance.

Sunday, 13 July 2008

Chelsea-Hackney Line results published

The Department for Transport has published their results for their updating of the Chelsea-Hackney route (aka Crossrail 2). The only real change is that the route via Sloane Square will continue to be safeguarded, in addition to the newly proposed route further south. The original consultation documents are here, including a nice set of detailed maps at the bottom.

It's important to remember that this is only a safeguarded route and not a proposal to build anything. At some point between now and 2025 it's likely a proposal will be made, and they may use the route safeguarded here, or they may do something entirely different. Decisions about the locations of stations, the choice of outer branches, the tunnel diameter and so on simply haven't been made yet.

Friday, 11 July 2008

Croxley Rail Link soldiers on

Hertfordshire County Council are about to submit a new business case for to the Department for Transport, less than six months after the last one, and three months after that was rejected for not being "compliant". The cost has gone up from £95m to £150m, suggesting the original bid was rejected for underestimating costs.

All they need now if for the DfT to agree to fund the bulk of the cost (£120m), which is exactly the position they've been in since forever. They've received a boost in that the East of England Regional Assembly have given their backing, which may or may not be worth anything.

The scheme is to divert the Metropolitan Line's Watford branch to Watford Junction by building a 500m connecting viaduct to link it up with an mile-and-a-half long disused branch line (pictured), which will need to be rebuilt. The new route includes two new stations. Here's a diagram of all the bits and pieces on Google Maps.

[via uk.transport.london]

Wednesday, 9 July 2008

Northern Line upgrade details

District Dave's tube forum has some lecture notes about progress on upgrading the Northern Line, given by the line's General Manager, Jeff "98.5% train reliability" Ellis.

The Northern Line is due to be fitted with a new signalling system called TBTC (transmission-based train control), which is the what provides the automatic operation of the DLR and is currently being fitted to the Jubilee Line (look for the telltale loops of cable between the tracks), which will allow trains to run closer together and therefore more frequently.

The rebuilding of Camden Town is mentioned, apparently in Jubilee Line Extension style, although not until TfL next budget period, which starts in 2013. This will allow the Northern Line split, and a train every 90 seconds (36 trains per hour) could be the result, though they'd need to buy more trains.

Rebuilding Clapham Common and Clapham North to rid them of their narrow island platforms (as was done at Angel and Euston) is also thought necessary in the near future.

Death of the Circle Line confirmed

In the latest issue of Modern Railways there's an interview with David Millard, manager of the Circle and Hammersmith & City Lines, discussing the ins and outs of the plans to turn the Circle Line into a Hammersmith-Edgware Road spiral (see diagram). That's right, a senior member of staff has confirmed it on record in a public forum. No more rumours, no more leaked internal documents. It's happening.

One consequence of the plan is an increase in the number of trains using Praed Street Junction and Edgware Road. The article mentions a proposed solution - run half of the District Line's services to Edgware Road only as far as High Street Kensington. However this will only be possible off-peak when demand is lower.

The timescale - like everything else in London - is to have it ready by 2012.

Update: I've just had another read of the article, and they say they could introduce it as early as December 2009.

Saturday, 5 July 2008

More on the Northern Line to Battersea

Annie Mole at Going Underground has been to Battersea Power Station to check out the developer's exhibition of plans for the site. She's posted photos of the information about the proposed Northern Line extension.

You can see on their tube map that, as I suspected, they're only connecting to the Charing Cross branch at Kennington. Most trains from that branch terminate at Kennington anyway, where they go round a huge loop to reverse, and it would be reasonably straightforward to plumb the extension into that loop rather than any of the running lines.

There's be no access to the Bank branch from Battersea, but there would be an easy cross-platform interchange at Kennington.

The exhibition is open for its last day today until 6pm, and includes a tour of the power station site. According to Annie, you may also be able to visit on the 13th and 19th. Check the developer's website for more details.

Update: I popped down there myself and here's a copy of the site transport plan, which shows the exact proposed route of the tunnels (click to enlarge):
Battersea station is on the south edge of the development where it could serve other parts of the local area. Above the key there's the outline of a second station, on Wandsworth Road bang underneath Vauxhall Sainsbury's.

Tuesday, 1 July 2008

TfL Board Papers: June 2008

TfL held its first board meeting since the Mayoral election last week, and the papers are online. Highlights:

Oyster PAYG on National Rail

  • The rollout of Oyster PAYG London wide will require work "at 240 National Rail stations [which] includes the installation of around 1,100 Oyster validators, over 600 ticket gate upgrades, ticket machine upgrades [...]"
  • A fares proposal for Oyster PAYG has been submitted by the train companies, and is expected to be signed this month (July).
  • "Southern has now agreed to allow installation of Oyster equipment to commence immediately."
  • The Mayor's planned summit with train companies will look at "harmonisation of passenger standards (fares and information) plus interchange security and policing", as well as the headline Oyster PAYG issue.
London Underground
  • "Prior to its introduction on the District line, the new Sub-Surface train will be introduced on the Metropolitan line (from 2010) and on the Circle and Hammersmith and City lines (both 2012)," as previously announced. This seems to contradict Modern Railways' claim of a change of plan.
  • The Northern Line is now the most reliable on the network, with 98.5% of services running as planned, thanks to the new timetable.
  • The opening of the Northern Ticket Hall at King's Cross St Pancras has been moved forward to December 2009 at the request of the Department for Transport, in time for the start of Kent High Speed rail services.
  • The first new Victoria Line train will be tested in service in January 2009.
  • Testing of the new Jubilee Line signalling system isn't going well, with only a 50% success rate.
London Overground
  • Ticketless-travel on the Gospel Oak to Barking Line is down from 15% to 1.7% since London Overground took over.
  • The first new London Overground train will be tested in Derby this month, though it's unclear when the first one will be tested in London.
  • A few seats will be removed from the existing trains this month (as discussed for the GOBlin) to increase standing capacity and reduce boarding times.
  • The new London Overground platforms at Stratford will open in December 2008. These allow the existing ones to be reused for the DLR extension to Stratford International.
  • The first section of new slab track for the East London Line extension was laid on 12 April.
Crossrail
  • A final Crossrail funding agreement is being prepared for signing in September.
  • They're trying to get the Crossrail Bill passed before Parliament breaks up on 22 July, but it's looking "increasingly tight"
  • The congestion relief plans for Tottenham Court Road tube station require powers granted by the Crossrail Bill.
DLR and Tramlink
  • Track work for the DLR Woolwich Arsenal extension is complete
  • Testing of the new DLR trains is being held up by getting electrical interference approval from London Underground at Stratford.
  • An immediate cleaning and refurbishment of the Croydon tram system is planned now TfL own it, to be carried out by existing operating contractor First.

Tuesday, 24 June 2008

Baffled Boris boffins dripping with sweat chuffed afoot fight to keep passengers fresh

TfL have put out their annual press release announcing the summer's cooling plans (cf. 2007, 2006). Despite the success Victoria's groundwater-based cooling system there's no sign of it being installed elsewhere; air-conditioned S-stock is still not due until 2010; tube trains are still too hard to cool; more industrial fans will be put in stations; more ventilation shafts will be reactivated; and generally that kind of thing.

Friday, 20 June 2008

Northern Line extension to Battersea Power Station proposed

The latest masterplan for the Battersea Power Station site has been unveiled by the poetically named new owners Real Estate Opportunities Ltd, and includes a surprising transport element:

Treasury Holdings UK is in discussions with Transport for London and other landowners in the Nine Elms about building an extension of the Northern Line from Kennington to bring the Tube into the heart of Battersea.
Looking at the map it's not a completely terrible idea. Kennington is where the two central branches merge so would be a good place to start the extension, most likely from the Charing Cross branch due to the track layout. I'd suggest an interchange at Vauxhall and a possible extension to the massive Chelsea Barracks redevelopment.

With construction of the development not due to start until 2012, it's more likely the site will be sold on again and this plan scrapped. The last owner's masterplan centred around upgrading Battersea Park railway station, which is one stop south of Victoria and a bit useless really.

There's a half finished website about the proposal here, which mentions an exhibition will open at the site this Wednesday.

Update: Today's londonpaper tells of a stop at "Wandsworth Road", though they can't mean the railway station of that name, since it's a long way out of the way.

Update 2 : More details

[Thanks to reader Jonathan for the tip off]

Thursday, 12 June 2008

Chesham shuttle replacement proposed

TfL have announced a proposal to replace the Chesham shuttle at the far end of the Metropolitan Line. Currently most trains from London run to Amersham, with Chesham served by a half hourly shuttle from Chaltfont & Latimer, with the odd through train during peak hours.

The proposal is to get rid of the shuttle and have the through trains alternate between going to Chesham and Amersham. Amersham is also served by Chiltern trains, so will have 4 trains an hour to London on weekdays rather than 6.

The impetus for this is the introduction of S stock to the Metropolitan Line in the next year or two, which will be made up solely of 8 car trains, rather than pairs of 4 car trains as now. The bay platform at Chalfont & Latimer used by the shuttle is only 4 cars long and would be difficult to extend.

The date given for the new service pattern is May 2009, which may indicate the Modern Railways story about the introduction of S Stock being postponed to after 2012 is nonsense.

Monday, 26 May 2008

TfL Question Time

Two TfL managers have just done an online Question Time session with an uncharacteristically eloquent and on-message section of the general public. There are quite a few interesting answers:

  • On tube cooling: "A new ventilation shaft is being installed at Liverpool Street"
  • On the Northern Line split: "We're currently reviewing the prospect of being able to separate the service and the likely timescales involved. [...]
    The option of fully separating the line would mean all Charing Cross branch trains would only go on to Edgware. All Morden - Bank trains would go on to High Barnet. [...]
    It's unlikely we would be able to implement any proposal before 2015 at the earliest."
  • On the King's Cross St Pancras Northern Ticket Hall: "This redevelopment programme is due to complete in December 2009" That's a little bit earlier than previous official dates.
  • On extending the Bakerloo to Watford Junction. The strategy guy says: "There are no plans at present [...] The Bakerloo line is being upgraded by 2020 and this would be the time to consider this"
    However the possibly-less-informed operations guy is slightly more positive: "At the moment we don't have funding to do this so London Overground services will continue to serve Watford Junction for a few years to come."